Utility to request reconsideration of line for Facebook site

Facebook

  SANTA FE, N.M. (AP) — A New Mexico electric utility wants state regulators to reconsider their rejection of the utility's proposal to have ratepayers pay half of the cost for installing a new transmission line to serve a Facebook data center and to instead have Facebook pay $39 million.

The Santa Fe New Mexican reports that Public Service Co. of New Mexico on Monday will refile its request with the Public Regulation Commission.

The 45-mile (72-kilometer) line between a switching station at Clines Corners and a new station in Sandoval County would supply electricity from renewable sources to the Facebook facility being built near Los Lunas.

An executive with a Facebook subsidiary has said the commission's decision raised serious concerns that could affect Facebook's commitments for the project.